Our Indicative project programme
Environmental Surveys
From Q1 2024 till Q4 2025
Planning Application Preparation
From Q1 2025 till Q4 2025
Community Consultation
Q1 2025 and from Q3 till Q4 2025
Planning Submission
Q4 2025
Planning Determination Period
From Q1 2026 till Q3 2026
Discharge of Conditions
From Q4 2026 till Q2 2027
Pre-Construction Works
From Q4 2026 till Q3 2027
Construction
From Q4 2027 till Q2 2028
Energisation
Q2 2028